Nova Minerals concludes winter freight to Estelle Project

Nova Minerals Limited has announced the successful completion of its 2026 winter freight mobilization to the Estelle Project in Alaska. All critical heavy equipment and supplies required for antimony ore mining, extraction, and processing under a Department of War (DoW) contract have now reached the site. Ore sorters have also been ordered, with delivery expected in the months ahead, and procurement has begun for the processing equipment destined for the downstream antimony refinery at Port MacKenzie.

Snow trail construction began in November, stretching from Willow to the Estelle Camp. Between March and early April, the team completed its largest-ever freight haul to the project -- roughly 1.5 million pounds of supplies and equipment.