Aluminum Copper Lead

No. 1 coke oven of Shanxi Gengyang coking project goes into production

According to ACRE, on the early morning of October 18th, the company's No. 1 coke oven at the Shanxi Jingyang coking project started with coal-charging. On the afternoon of October 19th, No. 1 coke oven output coke smoothly, which marked that the Shanxi Gengyang coking project went into full production.

Design, supervision and furnace-heat work of the project were wholly carried out by ACRE. In addition, the project includes four new top-loading coke ovens of 7.65 meters and ten top-loading coke ovens of 7.65 meters in Qingxu fine chemical industry park.